The brief
A first-floor practice in an office building whose equipment had shown earth faults several times and which needed an earth report to renew its licence. The building’s old earth pit had been put in years ago, its connection was buried under the car park’s concrete floor, and the first measurement showed a high figure.
How it was done
- 01 Existing earth resistance measured by the three-point method and the initial figure recorded
- 02 Multi-rod system designed instead of a deep pit, given the high water table
- 03 Four copper-bonded rods driven at proper spacing in the front planting bed and tied with bare copper
- 04 Buried joints exothermically welded, with an inspection box for future measurements
- 05 Dedicated earth conductor run to the practice board and the earth bar bonded
- 06 Final measurement and a written report with date, method and result
The outcome
Earth resistance came down to a low, stable figure and the equipment earth faults stopped. The written report went into the licence renewal file, and the inspection box makes periodic re-testing simple.