Motor
Three phase, 5.5 kW
Cable run
140 m
Enclosure rating
IP65
Duration
3 days
Location
Outskirts of Soumeh Sara, Gilan
Year
2025

The brief

The paddy irrigation pump had burnt out in two seasons running. Its feed was a thin flexible cable laid on the ground through the irrigation ditches, and the box beside the pump was a metal tin with no lid. The client wanted the pump supply done properly before planting season, so it would stop failing mid-season.

How it was done

  1. 01 Motor rated current measured and cable sized for the 140 m run and the permitted voltage drop
  2. 02 Armoured cable laid in a trench at proper depth with warning tape above it
  3. 03 IP65 enclosure mounted on a steel post above the field’s flood level
  4. 04 Motor circuit breaker set to rated current, plus a phase loss and imbalance relay
  5. 05 RCD protection and an earth rod beside the pump, with its resistance measured
  6. 06 Cable and motor winding insulation tested, and current on each phase recorded under load at commissioning

The outcome

The pump ran a full season without a stoppage. The network lost a phase once, and the relay took the pump off before it came to any harm. The insulation figures went to the client so next season’s pre-start test has something to compare against.

Contact

Describe the job and I will take it from there

One short call is usually enough to establish what the work is, how long it takes and roughly what it costs.

Call for an accurate estimate. If I am on a job and miss the call, I ring back as soon as I am off the ladder.