Standard
IEC 61439
Outgoing ways
14
PFC
Stepped capacitor bank
Duration
7 days
Location
Marjaghal, Soumeh Sara
Year
2024

The brief

A workshop with several motors, whose old board had neither discrimination nor adequate ventilation, and where loose terminations had been heating the busbars. The bill also showed a power factor penalty.

How it was done

  1. 01 Prospective fault current calculated and breaking capacity selected above it
  2. 02 Discrimination set between the main device and all fourteen outgoing ways
  3. 03 Every termination torqued to the manufacturer’s figure with a torque wrench
  4. 04 Fans and filters provided to match the calculated heat dissipation
  5. 05 Stepped capacitor bank fitted to correct the power factor
  6. 06 All conductors numbered and ferruled, with the drawing fixed inside the door

The outcome

A fault on one way no longer stops the whole workshop, and the power factor penalty came off the bill. The board was handed over with its drawing and parts list.

Contact

Describe the job and I will take it from there

One short call is usually enough to establish what the work is, how long it takes and roughly what it costs.

Call for an accurate estimate. If I am on a job and miss the call, I ring back as soon as I am off the ladder.