Points
58
Circuits
11 separate circuits
Duration
9 days
Earthing
New pit, resistance recorded
Location
Kasma, Soumeh Sara
Year
2023

The brief

A house with wiring several decades old, no RCD protection, and effectively the whole property on two circuits. Insulation had perished in several places, and Gilan humidity had done its part.

How it was done

  1. 01 Old wiring stripped out completely and new containment run
  2. 02 Split into eleven circuits: lighting, sockets, kitchen, cooling and fixed equipment
  3. 03 30 mA RCD protection on socket circuits and wet areas
  4. 04 New earth pit installed and its resistance measured with an earth tester
  5. 05 Metal pipework bonded and protective connections made
  6. 06 Every circuit insulation tested, with a single-line diagram and circuit schedule handed over

The outcome

The house now has shock protection, and one fault no longer darkens the rest of it. The insulation and earth resistance figures went to the owner as a baseline for the future.

Contact

Describe the job and I will take it from there

One short call is usually enough to establish what the work is, how long it takes and roughly what it costs.

Call for an accurate estimate. If I am on a job and miss the call, I ring back as soon as I am off the ladder.